Project Planning, Evaluation & Execution (3rd Party Developments)
Procedure
- Application is made to the Authority in respect of proposed development
- NPA responds with detail requirements for approval of the development
- On receipt of the requirements, the Authority evaluates concept of proposal and responds on approval of concept or otherwise
- The Authority forwards proposal to Federal Ministry of Transport (FMOT), ICRC, BPE and other required Government agencies, if outside Managing Director’s approval limits
- Proponent submits final requirements if there is approval to proceed further on development
- Authority carries out final evaluation of proposal based on availability of requirements
- The Authority forwards Final proposal to Federal Ministry of Transport and other required agencies for approval and transmission to FEC for approval or otherwise
- The Authority conveys final approval to proponent or otherwise
- The Authority monitors physical construction of developments.
Documentation
Structure Type A: Jetty, Quays, Breakwaters, Slipways including all Marine Structures
- Location map of proposed structure indicating adjoining development and hinterland connections
- Evidence of land ownership (C of O, lease status e.t.c)
- Bathymetric Survey map of the waterways
- Engineering /Coastal morphology/Dredging studies of the waterways of the proposed Structure location inclusive of information on wrecks, dredge volume, currents, wind, tides, siltation etc
- Topographical Survey map of land side of proposed Structure
- Structural Design/ Hydraulic Design Calculations for proposed structure based on the design vessels
- Structural Engineering Detailed drawings for proposed structure
- Geotechnical Investigation Report on the location for the development
- Environmental Impact Assessment (E.I.A) report on proposed development, inclusive of certification of EIA by the Federal Ministry of Environment.
Structure Type B: Buildings, Warehouses, Access Roads, including all Structures on Land
- Location map of proposed structure indicating adjoining development and road connections.
- Evidence of land ownership (C of O, lease status e.t.c)
- Engineering studies of the proposed Structure location etc
- Topographical Survey map of land area proposed structure
- Structural Design Calculations for proposed structure based on the intended use
- Structural Engineering Detailed drawings for proposed structure
- Geotechnical Investigation Report on the location for the development
- Environmental Impact Assessment (E.I.A) report on proposed development, inclusive of certification of EIA by the Federal Ministry of Environment
Notes: All documents should be submitted in 6 copies and should be certified by a COREN registered Engineer
Timeline
- Initial Response: Two (2) days
- Approval: Three (3) days
- Final evaluation of proposal: Ten (10) days
- Conveyance of Final Approval: One (1) day
Water treatment and supply
Procedure
- Request is made to the Port Manager (PM).
- Commercial department, who raises a debit note to the customer for payments.
- Water Treatment department delivers water on receipt of copy of debit note and evidence of payment
Documentation
- Debit note
- Payment receipt
Timeline
24 hours
Associated Charges
- 3USD/ton for Fresh Water
- 5USD/ton for Water at berth
- 10USD/ton at Midstream